Step 3: Schedule a site inspection
A site inspection will be conducted by Boulder County
Public Health (BCPH) staff. This inspection is an
important step in ensuring that the new septic system will not pose a risk
to the environment once installed.
This inspection will include a general review of the
conditions of the site, including checking that appropriate soil; is
used, that the system is not too close to wells, waterways, or
property lines; and that bedrock and groundwater are at
appropriate levels.
After the inspection, staff will review your
application, design requirements (if applicable), inspection
analysis, and data. This review can
take up to 14 days.
If all regulations are met,
BCPH will send you a postcard letting you know that your permit is ready to
be picked up at our
office.
You can pick up your permit at our office at 3450
Broadway, Boulder, Monday through Friday from 8 a.m. to
5 p.m.