DPR-11-0002QUINBY MD12-69HN

Location:12680 Baseline Road
Project Description:Development Plan Review to construct a new road to the production site; drill one additional gas and oil well (resulting in additional well head); expand existing tank facility by adding five oil tanks, two water tanks, two separators, and one compressor; and construct a 6-foot tall chainlink security fence with slats.
Application Date:Tuesday, August 16, 2011
Staff Planner:David Besley
Development Plan Review Documentation:
Director's Determination:
Determination Date:Wednesday, September 14, 2011
Appeal/Call-Up Deadline:Tuesday, September 06, 2011
Comments:Click here to send us your comments

Back to Development Applications Under Review