Docket Information

SI-13-0001XCEL ENERGY Boulder County West Main and Louisville West Main Natural Gas Pipeline Replacement

Location:Northeast Boulder County - 16 inch line entering the County at N. 95th Street, southwest to Airport Road, south to Oxford Road, then south along 95th Street to Isabelle Road. 12 inch line to extend along 95th Street between Baseline Road and Dillon Road. Please see application materials for specific project locations and information. • Sections 5, 8, 16, 17, 20, 21, 32 of Range 69W, Township 1N • Section 4, 5, 9, 16, 17 of Range 69W, Township 1S • Sections 6, 7, 17, 18, 20, 29, 32, 33 of Range 69W, Township 2N • Sections 4, 5, 8, 9, 17, 18, 19, 30, 31, 32 of Range 69W, Township 3N
Project Description:Areas and Activities of State Interest (1041) for the upgrade and replacement of approximately 24.3 miles of existing natural gas transmission lines. Project includes a new 16-inch line from the Boulder-Larimer County line to the Boulder-Roundup Valve Set on 95th Street south of Isabelle Road, a 12-inch line from the Boulder Junction Valve Set near North 95th Street and West Baseline Road to the Louisville Valve Set near South 96th Street and West Dillon Road, as well as 1.8 miles of smaller laterals.
Application Date:Friday, June 21, 2013
Staff Planner:Hannah Hippely
SI Application Information:
Referral Response Deadline:Friday, August 29, 2014
Planning Commission (PC) Public Hearing Date:
Staff Recommendation to the PC:
Planning Commission Action:
TBD
Board of County Commissioners (BOCC) Public Hearing Date:
Staff Recommendation to the BOCC:
To be posted here on week prior to the hearing.
Board of County Commissioners Action:
TBD
Public Hearing Parking Information:CAGID Parking Lot Information
Comments:Click here to send us your comments