North 83rd Street Flood Recovery - Permanent Construction

North 83rd Street over the Little Thompson River was destroyed during the 2013 flood event. Temporary culverts and a road were built post-flood. These structures will be replaced with a new bridge in 2016. Boulder County is working with FEMA on the project. 

The project will construct a new 250' long by 38' wide bridge that will withstand a 100-year flood event. The previous bridge that was washed out was 64' long by 28' wide and was rated to withstand a 10-year flood event. The county has been working with FEMA to ensure reimbursement for a majority of the project's final cost.   

ROAD/BRIDGE IS OPEN

Construction of the new bridge over the Little Thompson is ongoing, but the road/bridge is open to the public. The traveling public may still experience short delays if equipment is in the roadway. 
  • Project Contact - Andrew Barth, Transportation Public Information Officer, 303-441-1032 or email

Previous Meetings & Materials:

Project Contacts:


If you'd like to comment on this project or ask a question, use the online comment form or email or call either of the contacts below.