95th Street Bridge
Replacement Over Boulder Creek
The 95th Street Bridge
replacement project will replace the existing roadway bridge over
Boulder Creek between Valmont Road and south of Lookout Road with a new
structure that will include paved shoulders for bicycles. The new
structure is needed to remove the current weight restrictions and to
comply with the current technology for highway loading.
The existing structure of the 95th Street Bridge over
Boulder Creek was built in 1962 and is in need of replacement to meet
current and future traffic demands. The new structure will
accommodate two thru-lanes (one northbound and one southbound) and paved
bike lanes on each side. The new bridge will be slightly longer
and higher than the existing structure to increase its conveyance
capacity for flood events and decrease the potential occurrences of
flooding on N. 95th Street.
Bridge improvements are funded through Boulder County
Capital Improvements Program (CIP) and
Urban Drainage & Flood Control District CIP funds. The total
cost of the project is projected at just under $1.0 million and will be
constructed by DeFalco Construction Company.
It is anticipated that construction period for this
project will extend for approximately six months. N. 95th Street
will be closed to through traffic from August 3, 2009 through January
29, 2010 to maintain a safe work zone and minimize the time needed to
complete the construction project and its impact on the public.
N. 95th Street Bridge
Replacement Begins Work on Abutments Prior to Demolition of Bridge
Contractor will begin excavation for the north bridge
abutment Monday, September 21, no through vehicular, bicycle or
pedestrian traffic will be allowed to cross through the construction
zone until the road is reopened.
Clearance for the swallows nesting under the bridge
will allow demolition of the bridge components following Friday,
September 25. The Contractor is expected to begin disassembling
the bridge deck on Monday, September 28. The bridge will be out of
service for the duration of the project (currently projected to be
January 29, 2010).
The project work schedule is expected to be impacted
by the high water levels in Boulder Creek until November, when the creek
will convey only stormwater runoff without supplemental irrigation
water.
Please call Pam Hanson, Project Engineer at (720)
564-2652 with questions.
|