BoCo Alert System

Boulder County non-emergency offices will be closed on Monday, May 29 for Memorial Day.

Wagonwheel Gap Road Reconstruction

Wagonwheel Gap Road Reconstruction

The permanent reconstruction project is underway.

Travel During Construction

  • Work hours = 7 a.m. to 5 p.m. – Monday through Friday
    • Some Saturdays, but only when necessary
    • No work on major holidays
  • Wagonwheel Gap Road will be reduced to one lane in multiple locations
    • Flaggers and traffic signals will be used to move people through the work zone
    • Delays of up to, but not to exceed, 15-minutes
    • Will likely be much shorter – 3 to 5 minutes
    • Actual time based on length of work zone and speed of slowest traveler (likely cyclists)
  • Bow Mountain Drive will be fully closed at Wagonwheel while a new bridge is built
    • Anticipated dates = June through September 2017
    • Emergency service providers will be granted access
  • Emergency Service Providers will have immediate access at all times
  • Construction is anticipated to last until the fall of 2018

Reconstruction/Restoration Plans

JANUARY 13, 2017 – 100% Plans – These are construction ready plans, but they may not be final as small adjustments can still be made if needed. The overall plan set has been broken down into smaller sections to make it easier to download.

  • Pages 1 to 27 – Introduction, Symbol Key, Notes, Typicals, Quantities, Tabulations, Key Map, and Geometric Layout
  • Pages 28 to 53 – Removals & Resets and Roadway Plans & Profiles
  • Pages 54 to 82 – Driveway & Approach Grading, Speed Hump Details, Drainage Plans & Profiles
  • Pages 83 to 117 – Lion Point Grading, Drainage Details, Culvert Details, General Bridge Information, Bow Mountain Bridge Plans
  • Pages 118 to 140 – Lee Hill Approach Bridge Details and Wagonwheel Gap Bridge Details
  • Pages 141 to 173 – Retaining Walls
  • Pages 174 to 195 – Suggested Phasing Plan and Source Water Management Plan (SWMP)
  • Pages 196 to 225 – Cross Sections

Previous plan sets are available upon request

Previous Meetings & Meeting Materials:

Project Contacts/How to Comment:

  • Andrew Barth – Communications – 303-441-1032 – email
  • Alli Kelly – Project Engineer – 720-564-2651 – email

Wagonwheel Gap Road Flood Damages

Wagonwheel Gap Road September 2013 flood damages

Wagonwheel Gap Road September 2013 flood damages


Wagonwheel Gap Road September 2013 flood damages

Wagonwheel Gap Road September 2013 flood damages

Contact Us

Transportation Department

303-441-3900
Submit a question

Location

2525 13th Street
Boulder, CO 80304

Map & Directions

Hours: 8 a.m. - 4:30 p.m. M-F

Mailing Address

P.O. Box 471
Boulder, CO 80306